One of the main engineering systems are communication networks. They are also sometimes called low-current, since information currents pass through them, and not power ones. The voltage of such networks can be about 12 to 24 V. When installing external communication networks, it is necessary to take into account the basic requirements that apply to them:
Before laying such engineering systems, it is necessary to correctly develop an estimate for the installation of external networks. Only specialists will be able to calculate everything accurately and without errors, therefore, compilation services budget documentation It's best to order from them. A lot will depend on the qualifications of the contractor, so the search for an estimator must be approached as responsibly as possible.
Low-voltage networks today make it possible to create:
When drawing up an estimate for a communication network, it is necessary to calculate all the costs of installation and other work. It could be:
All this should be included in separate items when drawing up the estimate documentation.
In addition, it is very important to design the communication network to be installed. AT without fail location must be specified:
We must not forget that all commissioning work must be carried out in accordance with approved rules and standards. The same applies to the calculation of estimates for the communication network - everything should be calculated as accurately as possible. This can only be done in budget bureaus, where professionals in their field work. True, some independently carry out commissioning of equipment and calculation of estimates, but without some experience this is impossible to do.
We should never forget that during the laying of communication networks, only high-quality equipment should be used. This applies to:
Accordingly, all this should be taken into account when developing the budget.
The best estimators can be found on the Yudu website. Only proven performers are registered here, who are able to quickly and competently calculate the budget of the event installation work. You can order such services at the price that the customer is able to pay. Of course, each artist has their own prices, but they are not final.
C - the cost of building a cable line,
C1 - construction cost of the 1st section,
C2 - construction cost of the 2nd section,
C3 - construction cost of the 3rd section,
C4 - construction cost of the 4th section,
C5 - construction cost of the 5th section;
where H1 - standard 11-01-008-10,
L1 - length of 1 section of the route (4.3 km),
where H2 - standard 11-03-001-102,
L2 - length of 2 sections of the route (40 m),
where H3 - standard 11-01-004-10,
L3 - length of 3 sections of the route (8 km),
where H4 - standard 11-03-002-91,
L4 - length of 4 sections of the route (60 m),
where H5 - standard 11-01-008-10,
L5 - length of the 5th section of the route (3.5 km),
Kst - coefficient taking into account the cramped conditions for the production of work,
In electrical work, a huge amount of cable products is used: wires and cables, as well as cable channels, corrugated pipes, trays and boxes used to protect them. Of course, the cable products themselves have the largest assortment: there are thousands of nomenclature items that differ in type, brand, cross section and purpose of the cable. In this essay, we, of course, will not be able to find prices for all types of cables and wires. Let's try to better consider the most popular types of cables most commonly used in cost estimates:
UTP twisted pair;
Fiber optic cable;
Optical cable (FOCL);
SIP wiring;
Overhead line wires and lightning protection cables;
Power cable type VVG (ng) (LS);
Control KSSP, KVVG;
Wire PV3 yellow-green for grounding.
The listed cables, especially power VVG, have many modifications that differ in cross section, number of cores, incombustibility, power, etc. Almost each of them can be laid in different ways: openly and hidden under wallpaper, in ceilings, trays, corrugated pipes, cable channels. To protect cables in places where they pass through walls, steel sleeves are often used, which are cut from pipes with a diameter of 20-50 mm. Many power cables adapted to environmental conditions can be laid in a trench on a sandy base or without it. The places where cables pass on the ground are often marked with signal tape. Consider the option estimating the installation of cables using the example of UTP and fiber optic cable (FOCL):
Rationale | Name | Qty. | Main salary | EkMash | W/n Fur | Total |
TERm10-01-053-01 | Rope laying for outdoor cable routing | 100 m cable or wire | 56,23 | 2,63 | 0,1 | 123,82 |
rope cost | Rope for outdoor cable routing | m | 0.00 | 0 | 25 | |
TERm10-06-035-03 | Optical cable laying, weight of 1 m cable up to 2 kg | 100 m cable | 275,28 | 1287,5 | 1,14 | 2326,31 |
Commercial offer for Optical cable, LSZH | Optical cable 4 fibers, LSZH | m | 0.0 | 0.0 | 30 | |
TERm10-04-089-01 | Termination of solid fiber optic and UTP cable into SFP and RJ45 connectors | 10 cable ends | 0.00 | 134,65 | ||
TERm10-06-055-01 | Splicing fiber optic cable with number of fibers: 4 | 1 USSLK | 1250 | 8,84 | 3,53 | 1371,8 |
TERm10-01-055-02 | UTP cable laying, weight 1 m: up to 1 kg | 100 m cable | 181,49 | 87 4,2 | 0.00 | 1545,6 |
Price for Twisted pair UTP 5E outdoor (copper) | Twisted pair UTP 5E outdoor (copper) | 1 m cable | 0.00 | 35 |
Please note that in our example, the optical cable is laid along a cable, which is very typical for outdoor installation. Thus, we came across another type of cable laying, which can also be used in the preparation of estimates - this is cable wiring. Note that the work on setting up the laid lines of the fiber-optic cable is placed in the section of installation, and not commissioning, which, however, is very typical for part 10 "Communication networks". Here, installation prices often coexist with commissioning and configuration of devices, low-voltage networks, communication and telephony devices.
Another typical option that can be found in almost any estimate on electric installation work, is the laying of power wires in corrugated pipes.
Rationale | Name | Qty. | Main salary | EkMash | W/n Fur | Total |
TERm08-10-010-01 | Corrugated PVC Pipe Laying for Wire and Cable Protection | 100 m | 112,02 | 40,77 | 0,1 | 426,28 |
TSSTs-103-2408 | Flexible corrugated light pipes made of self-extinguishing PVC (IP55) FL series, 25 mm in diameter | 10 m | 0.00 | 0 | 23,41 | |
TERm08-02-412-02 | Pulling wire into laid pipes with a total cross section of up to 6 mm2 | 100 m cable | 40,69 | 4,66 | 1,14 | 61,87 |
TSSC-501-8482 | Power cable with copper conductors with PVC insulation and sheath, flame retardant, with low smoke emission, brand VVGng-LS, with a number of cores - 3 and a cross section of 1.5 mm2 | m | 0.0 | 0.0 | 5,52 | |
TSSC-507-2838 | Pipe clamps | 1 PC. | 0.00 | 7,4 |
Often the cable needs to be laid not in flexible corrugated pipes, but in stronger protective devices, such as trays or cable channels. For this, the TER territorial base has other rates. Laying cables and wires in trays is especially relevant for outdoor wiring. The following example of an estimate calculation just demonstrates the laying of cable products not inside the room, but from the outside (more precisely, at the point where the cables enter the building).
Rationale | Name | Qty. | Main salary | EkMash | W/n Fur | Total |
FERm08-02-147-11 | Cable up to 35 kV on installed trays with fastening along the entire length with a weight of 1 m of cable up to 2 kg | 100 m | 166,23 | 61,33 | 0,1 | 264,17 |
FERm08-02-155-01 | Sealing passages when entering cables into the room with a sealing mass | Sealing passages when entering cables into explosive premises sealing mass | 3.66 | 0 | 18,73 | |
FERm08-02-160-04 | Epoxy termination for 3-4-core cable with voltage: up to 10 kV, cross-section of one core up to 185 mm2 | 1 PC. | 26,74 | 4,66 | 1,14 | 32,14 |
FERm08-03-574-07 | Wiring by devices and connection of cores of cables or wires with a cross section of up to 150 mm2 | 100 pieces. | 782,69 | 34,74 | 0.0 | 953,37 |
In the previous budgeting example, we installed an outdoor cable in a tray and brought it into the building, sealed it and connected it to devices in the right places. Now consider the option when the UTP cable, power VVG or control KVVG must be laid in the cable channel indoors. For this case, there are direct prices, both for laying the cable channel and for installing the wire itself. Let's look at an example below:
Rationale | Name | Qty. | Main salary | EkMash | W/n Fur | Total |
TERm08-02-390-03 | Laying of a plastic box up to 120 mm wide | 100 m | 155,12 | 37,42 | 0,1 | 226,78 |
FSTS-509-1840 | Cable channel (box) "Electroplast" 100x60 mm | m | 0.00 | 0 | 15 | |
TERm08-02-390-01 | Laying of a plastic box up to 40 mm wide | 100 m | 124,29 | 29,9 | 1,14 | 175,75 |
FSTS-509-1841 | Cable channel (box) "Legrand" 20x12.5 mm | m | 0.0 | 0.0 | 8 | |
TERm08-02-398-01 | Laying wire in trays, cross section up to 6 mm2 | 100 m | 22,9 | 2,33 | 0.00 | 22,9 |
TERm08-02-398-02 | Laying wire in trays, cross section up to 35 mm2 | 100 m | 15,55 | 4,66 | 3,53 | 33,79 |
We looked at several examples of wiring, incl. in trays, boxes, corrugated pipes, on a cable, in a cable channel, as well as an external mounting method. I would like to dwell on the method of laying wires in a trench on a ready-made sand base. For these types of work there are direct prices from part 8 of the collection for installation electrical devices– they are easy to find in the collection. The only point is that these prices for laying wires in a trench are for power cables designed for higher voltage than most control and management cables. Therefore, it is not recommended to lay low-voltage cables along them, and for power ones, these prices will be just right. On this slightly optimistic note, I would like to end our short excursion into the industry estimated pricing in terms of laying cables VVG, UTP, SIP, PV3, KVVG and many of their analogues. By no means claiming to be the ultimate truth, we just tried to describe some of the most popular solutions when searching for prices on this topic. In general, as we have noticed, one of the features of using the TER, FER, GESN bases is the multivariance in the selection of prices for the same work (of course, in the absence of a direct price), so nothing prevents you from choosing one or another standard from the base yourself , and, perhaps, it will turn out to be more accurate and more appropriate than what we proposed. Thank you for your attention.
construction communication cable lightning
The scope of work statement is compiled to calculate the labor intensity for each type of work, to determine the required number of workers, machines and mechanisms, vehicles.
The bill of quantities of work is drawn up in the form of table 5.
Calculation of the cost of a channel-kilometer С, rub/(kan*km) is made according to the formula (22)
C \u003d P / N * L (22)
Calculation of C for the number of channels involved:
C \u003d 2386341.961 / 5340 * 324 \u003d 1.37 rubles / (kan * km)
Calculation of C for the maximum possible number of channels:
С=2386341.961/7200*324=1.02 RUB/(kan*km)
Table 5 - Estimate for the construction of the projected communication line
The name of indicators |
Total for the master. |
The cost of materials and equipment |
Salary |
|||
per unit ism |
per unit ism |
|||||
1. Cable by type |
||||||
2. Cable Laying |
||||||
3. Laying the cable in the trench |
||||||
4. Construction of a telephone sewer |
||||||
5. Cable laying in the sewer |
||||||
6. Construction of crossings over roads and rivers |
one transition |
|||||
7. Installation and measurement of the cable laid in the sewer and the ground |
||||||
8. Inflating the cable with air after installation |
amplifying area-current |
|||||
Wage |
||||||
overhead for wages 87% of 2 |
||||||
Total (1 + 1.87 2) = 3 |
||||||
Planned accumulation 8% from 3 |
||||||
Total estimate (1 + 0.08) 3 |
To provide 5300 HF channels between the cities of Orel - Voronezh, the project provides for:
1) cable laying KMB - 4;
2) the use of two transmission systems K - 3600;
3) at the first stage, use 5340 channels, and leave 1860 channels in reserve for further development;
4) place PMO - 2 in the city of Yelets;
5) place 107 NUPs along the route.
The project does not provide for protection of the cable from lightning discharges.
1. Mikhalev A.N., Komarov Yu.Z. Guide telecommunication systems: guidelines for the course project. Yekaterinburg: UrTISI GOU VPO "SibGUTI", 2007
2. Baron D.A. Construction of cable communication facilities. Directory. - M.: Radio and communication, 1988.
3. Grodnev I.I. Communication lines. - M.: Radio and communication, 1993.
4. Filatova T.P. Atlas highways Russia - Federal State Unitary Enterprise "Omsk Cartographic Factory", 2006
5. Internet.
6. Ionov A.D. Design of cable communication lines. Tutorial: Novosibirsk, 1995.